Title: ORDER approving Change Order No. 01, dated March 11, 2024 with D.N.P. Incorporated, for the Sheriff's Work Center, New Generator, for an increase of $16,560.00, to swap out the existing Automatic Transfer Switch in NEMA 1 enclosure for a new ATS with a NEMA 3R enclosure, and authorizing the Board President to execute the same, as recommended by Jaclyn Turner, P.E., Harrison County Engineer.
Attachments: 1. Signed CO 1 2239 2024-03-14

Title

ORDER approving Change Order No. 01, dated March 11, 2024 with D.N.P. Incorporated, for the Sheriff's Work Center, New Generator, for an increase of $16,560.00, to swap out the existing Automatic Transfer Switch in NEMA 1 enclosure for a new ATS with a NEMA 3R enclosure, and authorizing the Board President to execute the same, as recommended by Jaclyn Turner, P.E., Harrison County Engineer.