Legislation Details

File #: 24-3259    Version: 1 Name:
Type: Order Status: Passed
File created: 4/26/2024 In control: Engineering
On agenda: 5/6/2024 Final action: 5/6/2024
Title: ORDER acknowledging receipt of the close-out documents transmitted by Twin L Construction, Inc., for the Window & Door Replacement Harrison County 2nd Judicial Courthouse project approved by Jaclyn Turner County Engineer, and authorizing execution of the following documents related thereto: a) Payment of $18,475.01 to Twin L Construction, Inc., Application for Payment No. 2 (final), payable from 001-121-581 b) Contractor’s Affidavit of Debts and Claims c) Consent of Surety to Final Payment d) Contractor's Affidavit of Release of Liens e) Workmanship Warranty f) Attachment 1 (Sub Contractor Agreement Pas-Point Glass - Workmanship Warranty (5 Years) g) Certificate of Substantial Completion
Attachments: 1. HARR CON FINAL (002), 2. SUB COMP HARR CO, 3. Twin L Warranty

Title

ORDER acknowledging receipt of the close-out documents transmitted by Twin L Construction, Inc., for the Window & Door Replacement Harrison County 2nd Judicial Courthouse project approved by Jaclyn Turner County Engineer, and authorizing execution of the following documents related thereto:

 

     a)  Payment of $18,475.01 to Twin L Construction, Inc.,

          Application for Payment No. 2 (final), payable from 001-121-581

     b)  Contractor’s Affidavit of Debts and Claims

     c)  Consent of Surety to Final Payment

     d)  Contractor's Affidavit of Release of Liens

     e)  Workmanship Warranty

      f)  Attachment 1 (Sub Contractor Agreement

          Pas-Point Glass - Workmanship Warranty (5 Years)

     g)  Certificate of Substantial Completion