Title: ORDER approving Change Order 1 for the ARPA/MCWI Beach Outfall Repairs and Upgrades project to include a pay item for flat concrete work for driveways needed to access other work from Highway 90 in accordance with recently approved MDOT permits. Contract increase will be a total of $8,887.50 and will be fully grant funded. Authorize the Board President to execute documents.
Attachments: 1. CO#1 (entire package)

Title

ORDER approving Change Order 1 for the ARPA/MCWI Beach Outfall Repairs and Upgrades project to include a pay item for flat concrete work for driveways needed to access other work from Highway 90 in accordance with recently approved MDOT permits.  Contract increase will be a total of $8,887.50 and will be fully grant funded.  Authorize the Board President to execute documents.