Legislation Details

File #: 25-0315    Version: 1 Name:
Type: Order Status: Passed
File created: 2/18/2025 In control: Engineering
On agenda: 3/3/2025 Final action: 3/3/2025
Title: ORDER approving Change Order No. 1 with Apple Construction for the Flatbranch Regional Pump Station project to avoid installing pressure sewer pipe under storm drain structures. Bore will be 14” HDPE rather than 12” C-900, resulting in an increased cost of $60,804.75. Grant funding is available to cover the cost of the change; and authorizing the Board President to execute the same.
Attachments: 1. Flatbranch CO 1 Partially Exec

Title

ORDER approving Change Order No. 1 with Apple Construction for the Flatbranch Regional Pump Station project to avoid installing pressure sewer pipe under storm drain structures. Bore will be 14” HDPE rather than 12” C-900, resulting in an increased cost of $60,804.75. Grant funding is available to cover the cost of the change; and authorizing the Board President to execute the same.