Title:
|
ORDER approving attached Supplemental Agreement No. 1 for Lane Construction Company of Mississippi, Inc., for Canal Road and Landon Road Intersection, Project No. SA-24(59), to add 20 working days to the contract time due to contractor encountering unsuitable soil conditions and unexpected utility conflicts resulting in additional work beyond the work set forth in the original contract, as recommended by Douglas K. Rackley, P.E., State Aid Engineer, and authorizing the Board President to execute same.
|