File #: 25-1849    Version: 1 Name:
Type: Order Status: Passed
File created: 9/30/2025 In control: Engineering
On agenda: 10/6/2025 Final action: 10/6/2025
Title: ORDER accepting and approving Final Pay Application No. 6, Summary Change Order No. 2 to reflect actual quantities used on the project, and all closeout documents for the ARPA / MCWI North Carr Bridge Drainage project with JE Talley Construction, Inc., as recommended by Covington Civil and Environmental as attached. Authorize Final Payment in the amount of $24,205.54 and authorize Board President to execute all included documents.
Attachments: 1. Change Order #2-Summary North Carr, 2. Pay Application #6 Recommendation of Payment, 3. North Carr Bridge Road - PA #6-Final, 4. NORTH CARR BRIDGE AS-BUILTS, 5. Closeout Documents North Carr Bridge Road, 6. Pay Application #6 Recommendation of Payment (003)

Title

ORDER accepting and approving Final Pay Application No. 6, Summary Change Order No. 2 to reflect actual quantities used on the project, and all closeout documents for the ARPA / MCWI North Carr Bridge Drainage project with JE Talley Construction, Inc., as recommended by Covington Civil and Environmental as attached. Authorize Final Payment in the amount of $24,205.54 and authorize Board President to execute all included documents.