Title: ORDER accepting and approving Final Pay Application No. 5, Summary Change Order No 1 to reflect actual quantities used on the project, and all closeout documents for the ARPA / MCWI White Plains Drainage project with JE Talley Construction, Inc., as recommended by Covington Civil and Environmental as attached. Authorize Final Payment in the amount of $58,710.64 and authorize Board President to execute all included documents.
Attachments: 1. White Plains Road - PA #5-Final1, 2. Pay Application #5 Recommendation of Payment, 3. WhitePlains Closeout Documents, 4. WHITE PLAINS AS-BUILTS, 5. Change Order #1 (Summary) White Plains

Title

ORDER accepting and approving Final Pay Application No. 5, Summary Change Order No 1 to reflect actual quantities used on the project, and all closeout documents for the ARPA / MCWI White Plains Drainage project with JE Talley Construction, Inc., as recommended by Covington Civil and Environmental as attached. Authorize Final Payment in the amount of $58,710.64 and authorize Board President to execute all included documents.