File #: 25-1860    Version: 1 Name:
Type: Order Status: Passed
File created: 10/1/2025 In control: Reports to the Board
On agenda: 10/6/2025 Final action: 10/6/2025
Title: Doug Rackley, Rackley Engineering LLC, discussed Wetland Mitigation Credits needed for the Landon Road Bridge Replacement Project SABP-24(01) for 0.693 acres of bottomland hardwood credits in the amount of $5,504.00. After discussion, the Board adopted an ORDER authorizing and approving the purchase of 0.693 credits from Wetland Solutions Holdings, LLC., in the amount of $5,544.00.
Attachments: 1. wetland credits to BOS

Title

Doug Rackley, Rackley Engineering LLC, discussed Wetland Mitigation Credits needed for the Landon Road Bridge Replacement Project SABP-24(01) for 0.693  acres of bottomland hardwood credits in the amount of $5,504.00. After discussion, the Board adopted an ORDER authorizing and approving the purchase of 0.693 credits from Wetland Solutions Holdings, LLC., in the amount of $5,544.00.