File #: 25-2283    Version: 1 Name:
Type: Order Status: Passed
File created: 12/2/2025 In control: Engineering
On agenda: 12/8/2025 Final action: 12/8/2025
Title: ORDER approving Change Order 2 with DNA Underground, LLC, for the ARPA/MCWI Hwy 67 / Tradition Area Regional Sewer Expansion project and authorizing Board President to execute. Change order increases the contract value by $766,180.00 and adds 100 contract days. This will offset quantity under runs in the existing contract scope, and grant funding is available to fully cover the balance.
Attachments: 1. CO#2

Title

ORDER approving Change Order 2 with DNA Underground, LLC, for the ARPA/MCWI Hwy 67 / Tradition Area Regional Sewer Expansion project and authorizing Board President to execute.  Change order increases the contract value by $766,180.00 and adds 100 contract days. This will offset quantity under runs in the existing contract scope, and grant funding is available to fully cover the balance.