File #: 26-0136    Version: 1 Name:
Type: Order Status: Passed
File created: 1/27/2026 In control: Engineering
On agenda: 2/2/2026 Final action: 2/2/2026
Title: ORDER taking off the table the approval of Change Order 5 for the ARPA Menge Avenue Sewer System project adding 110 calendar days to the contract of Southern Colonial Construction, LLC, as recommended by Chiniche Engineering & Surveying, related to adjustments to the contract in previous change orders and field adjustments and authorizing the Board President to execute documents.

Title

ORDER taking off the table the approval of Change Order 5 for the ARPA Menge Avenue Sewer System project adding 110 calendar days to the contract of Southern Colonial Construction, LLC, as recommended by Chiniche Engineering & Surveying, related to adjustments to the contract in previous change orders and field adjustments and authorizing the Board President to execute documents.