Title:
|
ORDER taking off the table the approval of Change Order 4 for the ARPA Kiln Delisle Sewer System project adding 70 calendar days to the contract of Southern Colonial Construction, LLC, as recommended by Chiniche Engineering & Surveying, related to adjustments to the contract in previous change orders and field adjustments, including extended manufacturing and delivery lead times and authorizing the Board President to execute documents.
|