Title: ORDER taking off the table the approval of Change Order 4 for the ARPA Kiln Delisle Sewer System project adding 70 calendar days to the contract of Southern Colonial Construction, LLC, as recommended by Chiniche Engineering & Surveying, related to adjustments to the contract in previous change orders and field adjustments, including extended manufacturing and delivery lead times and authorizing the Board President to execute documents.

Title

ORDER taking off the table the approval of Change Order 4 for the ARPA Kiln Delisle Sewer System project adding 70 calendar days to the contract of Southern Colonial Construction, LLC, as recommended by Chiniche Engineering & Surveying, related to adjustments to the contract in previous change orders and field adjustments, including extended manufacturing and delivery lead times and authorizing the Board President to execute documents.