Title: ORDER approving Change Order 4 for the ARPA Kiln Delisle Sewer System project adding 70 calendar days to the contract of Southern Colonial Construction, LLC, as recommended by Chiniche Engineering & Surveying and Jaclyn Turner, County Engineer, related to adjustments to the contract in previous change orders and field adjustments, including extended manufacturing and delivery lead times and authorizing the Board President to execute documents.
Attachments: 1. 15-001-09 Kiln Delisle CO 4 Time Extension request 12.24.25 signed

Title

ORDER approving Change Order 4 for the ARPA Kiln Delisle Sewer System project adding 70 calendar days to the contract of Southern Colonial Construction, LLC, as recommended by Chiniche Engineering & Surveying and Jaclyn Turner, County Engineer, related to adjustments to the contract in previous change orders and field adjustments, including extended manufacturing and delivery lead times and authorizing the Board President to execute documents.