File #: 26-0220    Version: 1 Name:
Type: Order Status: Passed
File created: 2/4/2026 In control: Engineering
On agenda: 2/9/2026 Final action: 2/9/2026
Title: ORDER approving the final plat and related documents for The Village at Spring Hill Subdivision, Phase 2, located in Section 6 Township 6 South, Range 11 West in Supervisor Voting District 5, First Judicial District of Harrison County, Mississippi, as recommended by Jaclyn Turner, P.E., Harrison County Engineer, with the condition that remaining punch list items are completed and verified, and all outstanding documents are on file prior to filing the plat, and authorizing the Board President to execute same: · Final Subdivision Plat · Health Department plan approval (water), dated January 27, 2022 · Health Department Final Approval Letter (to be completed with final phase) · DEQ plan approval (sewer), dated January 25, 2022 · DEQ Final Approval Letter (to be completed with final phase) · Great River acceptance letter (water & sewer), dated January 16, 2026 · Maintenance Bond in the amount of $24,500 · Asphalt Bond in the amount of $55,000 · Power company agreement with Coast Electric...
Attachments: 1. 03a Health Dept, 2. 03b MDEQ, 3. 03c Great River, 4. 05 CEPA Contract - Phase Two, 5. 02 Plat The Village, 6. Villages Bonds, 7. 07 Road info, 8. 01 Check Recording Fee The Village

Title

ORDER approving the final plat and related documents for The Village at Spring Hill Subdivision, Phase 2, located in Section 6 Township 6 South, Range 11 West in Supervisor Voting District 5, First Judicial District of Harrison County, Mississippi, as recommended by Jaclyn Turner, P.E., Harrison County Engineer, with the condition that remaining punch list items are completed and verified, and all outstanding documents are on file prior to filing the plat, and authorizing the Board President to execute same:

 

•                     Final Subdivision Plat

•                     Health Department plan approval (water), dated January 27, 2022

•                     Health Department Final Approval Letter (to be completed with final phase)

•                     DEQ plan approval (sewer), dated January 25, 2022

•                     DEQ Final Approval Letter (to be completed with final phase)

•                     Great River acceptance letter (water & sewer), dated January 16, 2026

•                     Maintenance Bond in the amount of $24,500

•                     Asphalt Bond in the amount of $55,000

•                     Power company agreement with Coast Electric Power Association

•                     Final Street names and lengths list

•                     Final Plat Recording fee

•                     Inspection report of all punch list items complete