Title:
|
ORDER approving Change Order 4 with Specialty Contractors & Assoc., Inc., for the MCWI/ARPA Beach Outfall Repairs & Upgrades project, adding outfall locations to the contract and reducing the contract time to align with state funding limitations. Change Order increases contract value by $1,044,725.10 and reduces contract time by 37 days, recommended by BMA and Jaclyn Turner, County Engineer, and authorizing the Board President to execute documents.
|