Legislation Details

File #: 26-0926    Version: 1 Name:
Type: Order Status: Passed
File created: 6/3/2026 In control: Engineering
On agenda: 6/8/2026 Final action: 6/8/2026
Title: ORDER approving final summary change order #5 with Southern Colonial Construction, LLC, for the MCWI/ARPA Kiln-Delisle Road Sewer project, resolving final field quantities used, reducing the contract amount by $53,491.74, and authorizing the Board President to execute same.
Attachments: 1. 15-001-009 Kiln Delisle Final Qty Adj Deductive CO5

Title

ORDER approving final summary change order #5 with Southern Colonial Construction, LLC, for the MCWI/ARPA Kiln-Delisle Road Sewer project, resolving final field quantities used, reducing the contract amount by $53,491.74, and authorizing the Board President to execute same.