Title:
|
ORDER approving final project closeout documents for ARPA/MCWI Firetower Sewer Project with LJ Construction, Inc., as recommended by Chiniche Engineering & Surveying and Jaclyn Turner, PE, County Engineer, and authorize Board President to execute relevant documents. Approvals include Final Pay Application #10 in the amount of $148,279.03 from account 072-384-581 and final summary change order No. 5 increasing the contract by $510,316.38 to reflect final quantities used during construction.
|