Legislation Details

File #: 26-1744    Version: 1 Name:
Type: Order Status: Passed
File created: 9/29/2026 In control: Sand Beach
On agenda: 10/5/2026 Final action: 10/5/2026
Title: ORDER approving Change Order #2 with J.E. Borries, Inc., for the James C. Simpson, Sr. Pier Replacement Project, adding material and installing metal roof to match Gateway towers in the amount of $9,500.00, and adding an additional 14 calendar days to the contract as recommended by Trey McKnight, Sand Beach Director, and BMA Consulting Engineers, and authorizing the Board President to execute same.
Attachments: 1. BMA Change Order

Title

ORDER approving Change Order #2 with J.E. Borries, Inc., for the James C. Simpson, Sr. Pier Replacement Project, adding material and installing metal roof to match Gateway towers in the amount of $9,500.00, and adding an additional 14 calendar days to the contract as recommended by Trey McKnight, Sand Beach Director, and BMA Consulting Engineers, and authorizing the Board President to execute same.