Title:
|
ORDER approving construction change directives for work at the Harrison County Diversion Center & Health Department, as recommended by Eley Guild Hardy Architects, and authorizing the Board President to execute same:
a) Change No. 1 for a decrease in the amount of $53,121.82 to the contingency allowance to J.W. Puckett & Co.’s contract for listed changes.
b) Change No. 2 for a decrease in the amount of $54,930.00 to the contingency allowance to J.W. Puckett & Co.’s contract for listed changes.
|